Skip to main content

Quality Check Points in Production.

When end customers or consumers purchase a garment they look for quality first. So, to have a satisfied customer, retailers must keep only quality product in their shops. For defective goods supply Buyer can penalize supplier & It might cost the factory lot of money and goodwill. So the manufacturers take care for garment quality at each stage of production. In maximum cases buyer inspects shipment at factory before accepting the finished garments. Whatever defects found in the final inspection, it is the cumulative figure of previous processes. So it is very important to rectify defective pieces at process where it occurred instead of in the finishing.

Lot of people and machines are involved in producing a garment for this defect may come. There is an obvious chance of making few faulty garments in a batch due to faulty machine or human intervention. The defective pieces can be corrected by repairing or changing defective parts. But re-work costs money and time. These both increase inefficiency of the company. And if one defect passed through initial process without detecting and correction and process goes on then at the later stages repair cost will be much more than detecting it in initial stage.


Production process starts after receiving of fabrics and end after dispatching of packed garments. Generally export house put quality check points at the end of each process to ensure that only quality pieces move to the next process. Department wise quality check points have been explained in the following.



Fabric Store
    100% fabric inspection with 4 point system.
Trim & accessories
-   Trims inspection Trim supplier & factory both side (100% : 10%)
Cutting Room    
     Marker checking
     Cut parts checking or audit
     Bundle inspection
Printing and Embroidery
    100 % inspection of printing & embroidery panels
Sewing Department
     Inline check point (at critical operation)
     Roaming checking (Random checking)
     Needle point check (Traffic Light System)
     End of Line checking (100%)
     Audit of checked pieces
Finishing Department
     Initial finishing inspection 
     2 Hours Carton complete goods Audit
     Final finishing inspection 
     Internal shipment audit



  1. Fabric Store: In the fabric store fabric is being checked before issuing it to cutting department. In general not all the fabric is checked. Usually 10% of fabrics are checked for good fabric suppliers. For power loom fabric and printed fabric 100% checking is done. Fabrics are checked in flat table, flat table with light box or on fabric checking machine. 4 point system for fabric inspection is used to measure the quality level of the incoming fabric.
  2. Trims & Accessory: Trims quality is also very important for having a quality garment. Trims inspection is done randomly against the given standards, like color matching. But for trims and accessories quantity checking is essential.
  3. Cutting Room: It is said that cutting is the heart of production. If cutting is done well then chances of occurring defects in the following processes comes down. In cutting room, check points are – i) marker checking, ii) cut part audit and iii) bundle checking.
  4. Printing & Embroidery Checking: Printing & embroidery is not a compulsory process. If printing & embroidery is done in fabric form then printing & embroidery is being checked in fabric store. For knits garment, maximum printing & embroidery is done in cut panels. So before issuing cuttings to sewing department, each panel is being checked properly. Defects that are found here is print & embroidery placement, color matching, misprint or print overlapping or shade variation.
  5. Sewing Department: Checkpoints in the sewing departments are as following.
  • Inline inspection: In assembly line generally check pints are kept for the critical operations. In these checkpoints, 100% checking is done for partially stitched garments and defect free pieces are forwarded to the next process. This type of checking is used for high value garment.
  • Roaming inspection: In this case checkers roam around the line and randomly check pieces at each operation.  
  • Traffic light inspection system: Very few garment manufacturer use this inspection system. In this system each operator is given a card for measuring their quality performance. Quality checker goes to the operator and do random check for few pieces and according to the inspection result, checker marked red or green on the card following rating criteria.
  • End of line inspection or table checking: A checker checks completely stitched garment at the end of the line. 100% checking is done here,
  • Audit of the checked pieces: Very few manufacturers follow this audit procedure but it is very essential checkpoint to assure that only 100% inspected garment are sent to finishing from sewing department. And all defective pieces are repaired before sending to finishing.


   7. Finishing Department: Check points in finishing department consists
  • Initial finishing inspection: checking done prior to pressing of the garment at finishing room is known as initial finishing.
  • Final finishing Inspection: After pressing garments are again checked and passed for tagging and packing.
  • Hourly Complete Carton Audit: Every 2 - 4 hours (As buyer requirement) Supplier QC dept. done this audit to ensure the hourly complete carton quality. 
  • Internal final audit: After garments are packed up to certain quantity, quality control team, do audit of packed garments. This process is carried out to ensure that before handing over shipment to buyer QC
If the completed work is being checked at each process and defective pieces are corrected before handing to the next process than at the end of production there is very little chance to have a defective at final inspection stage.

Comments

Popular posts from this blog

H&M SUPPLIER COLOR GUIDELINE

H&M has established this Colour Guideline to guide suppliers to achieve a quicker and better result in their colour work. For H&M Cosmetic products a separate Colour Guide Book is available. The guidelines and requirements in this Colour Guideline apply to all products in textile, leather/suede, plastic, bone, wood, metal, straw, paper etc. Colour evaluation using instrumental method should be used when applicable. All parts of a product are equally important to check according to the same guidelines; shell, details, accessories (including: threads, buttons, badges, zippers, interlinings, drawstrings, stoppers) etc. Therefore these guidelines are made for everyone involved in the colour process – garment makers, accessory suppliers, dyers, print houses, embroidery units etc. Each supplier to H&M is responsible for informing all of their suppliers and subcontractors about the content of these guidelines and requirements and to make sure that they al...

How Can Improve Production Quality

To become quality conscious, it might look at improving existing quality standards at various stages of manufacturing process. Producing a good quality product is a result of combined efforts of management, employees and workers by developing system, implementing good practices in floor and setting up standards.  Following tips can help to improve quality at production. Communicate the importance of quality production to your employees and floor workers, and explain quality expectations by the management.  Maintain a clean and dry workplace, including storage rooms and shipping areas.  Select and utilize appropriate equipment in cutting, sewing and finishing processes.  Provide appropriate tools, machines and equipment to each department. Provide on-the-job training to workers for new comer with existing.  Plan an ongoing program for machine maintenance.  Establish agreed-upon quality standards with all fabric ...

Cutting Quality Control & Re-cut procedure.

Cutting Quality Control: To be established a work process by which QC personnel able to run in a same path for continuous improvement.  The procedure can be control / feedback to cutting to produce smoothly & Good Quality production. Responsibility :  The responsible person in-charge of related department. Preparation for Bulk cutting: v   According cutting plan cutting Executive collects Approved sample, manufacturing order sheet, approved paper pattern / hard pattern & Marker paper with ratio chart. v   As per Order Qty. cutting Executive collects fabrics from WH & relaxes the fabric according estimated time. v   QA checks between ratio paper, marker paper, hard pattern & fabric inspection report. He confirms the marker with signature. v   QC makes mock up by style related parts to be check & ensure parts Shading. If have taken approval from Quality Manager or Merchandiser. v   According cutting plan ...