Purpose is to establish a standardized work process for good
team working. Scope is the procedure
will help to achieve our particular Goal.
Responsible section
in charge is responsible to implement the policy in production unit.
Preparation of Input:
v As per Input plan QA’s CMS, Trims
Card, Construction Sheet, How to Measure, collects BOM, measurement spec.
v As per production plan Quality Manager
Will collects approved sample.
v QA, QAM, TC, MC & Production
Responsible attend in the PP meeting. Meeting minutes Translate in local language
to line supervisor & Quality inspector.
Layout time:
v All Lay-out Responsible (Quality, M/C,
T/C, and Line QC Prod.) should be present in the line.
v QA & technician give technical
measurement on process.
v Quality & production T/C gives
process standard on each process. QA will counter check that standard is
correct.
v After completed 1st bundle
Quality Executive & Quality Manager will check measurement & each
process with Measurement Chart and styling.
v Quality Manager calls 1st
production meeting with all respective people & give cutting permission
also.
In Process Quality Control:
v After received new input In line QA
checks cut panel with the paper pattern & accessories with approved Trim
Card
v Every day morning In line QA checks
all needle point, SPI, tension by loose fabric. If found any problem inform
mechanic with record.
v Checks new operator in process.
v Check all technical measurement in
process has corrected with record.
v Checks end table QC reports &
finding problems. Take action in process as per their finding.
v Do completed garments measurements
& share with QC if there any discrepancy.
In Process Traffic light:
v QA pull from the bundle 10/7 Pcs
Randomly.
v QA Checks with operation standard
about workmanship & measurements, if there no defects QA keeps the garments
in same place & fill ups her audit sheet by marking green color.
v If QA gets at least one piece defects,
he calls supervisor & show him. By the time she fill ups her audit sheet by
marking Yellow color with defect code,
v If QA gets at 2 piece or more defects,
he calls supervisor & show him. By the time she fill ups her audit sheet by
marking RED color with defect code & stop the machine. Note – For Traffic
Light refer to “Traffic Light System”
post.
v Production Executive & Technician
goes the process & advise the operator, he also corrected the process as
per standard & put his signature on audit sheet by mentioning reason of
problem & how to rectify. Then operator makes another Bundle and calls QA
for inspection.
v QA checks 10/7 pcs by same method if
there no defects operator works continue but she should rectify the finding
defects by QA. QA fill ups her audit sheet a Green marks. If QA gets again
problems then QA Marks again red on her audit sheet & stopped the
operation. QA informs Quality Manager & technician and Production Manager,
they take necessary steps.
v Being operator gets one yellow; QA
goes that process for next bundle / follow up. He/she checks 10/7 pcs randomly.
If there no defects QI fill ups her audit sheets by another Green mark.
v Line QA Make a Measurement Report.
v End of the day in process QA makes
highest three defective process & make report to submit QA Manager.
Inspection
by End-Line QC:
v End table QA will do measurement 100 %
Garments on Leg, Waist, Under bust, Chest, Bottom or specially mention point.
v If he/she gets any discrepancy inform
to inline QA or Line Production Controller.
v End table QC has taken clear idea from
QA Executive and Quality Manager about her check point & how to measure
from 1st production of a style.
v End table QC follows Clock wise
Checking Method.
v She collects necessary documents: End
table audit sheets, CMS, measurement spec, PO chart, measurement tape, arrow
sticker, etc. from QA executive
v She/he checks garments by the sequence
as per advised.
v She/he fill ups hourly Inspection
report.
v End table QC gives production
Controller hourly defect quantity by taking signature from her.
v End-line QC also taken rectifies
quantity from production controller by estimated time & put record on
Inspection report.
v End table QC confirms hourly QC pass
on her audit sheet.
v In case of any damage garments QC
keeps those are separately, end of day she gives all damaged garments to
Quality Executive.
C.P.R:
v Line QA Check all cut panel when
coming from cutting.
v If found the any cut panel reject he
or she recorded on inspection sheet.
v Segregate all reject cut panel.
v Cut Panel inspection Record with
reject parts show in front of Quality Manager.
v Quality Manager will call Cutting
responsible and discus with them how to control it and when need to re-cut.
v All Reject Panel Return to cutting
with record.
v P. R should be re-cut daily basis and
return to sewing floor PO wise.
C.B.R:
v Quality Manager will review reject
garments and segregate which one is repairable and which one is need to re-cut.
v To take reject garments discussed with
cutting responsible and advice how many pieces need to re-cut when will
complete the re-cut.
v Quality manager make sure all CBR
should be re-cut complete PO wise don’t waiting for next PO.
v If have no fabric available in cutting
discussed with Merchandiser and fabric responsible, they are confirm is
available or not.
v If have fabric is available in fabric
store quality manager will make a Po sheet and send the mail to merchandiser
with fabric responsible.
v If have no Fabric is available in
fabric store or merchandiser discuss with GM and get the approval from him for
dying and inform to cutting after dying should be complete all CBR as per PO.
v
Quality Manager will monitoring this
process will complete as per
schedule
Comments